Hi everyone,

 

Last time, I had a question about changing the default PM pricing.

 

Austin was helpful by leaving this comment:

"To change the default PM pricing for planning total savings, use Policy --> Analysis --> Hardware Costs. There is a field for the value of host hardware cost that can be changed.

I hope this answers your question!

Austin"

 

Now, I was wondering if changing the default PM pricing would affect any portion of the analysis for planning? Or will it just simply affect the "Total Savings" category that appears on top of plan? I know that VMTurbo uses some "price" techniques to perform analysis.

 

Thanks again for all your help!